KUKL PID WORK PROGRESS

WORK PROGRESS SUMMARY
BDS: 49.94 km out of 60.6 km
DNI: 612.80 km out of 670 km

 Package: BDS 2

Narayangopal Chowk to Machhapokhari By-pass Balaju
Today: 6 m To Date: 2771 m Total: 3425 m
Pipe Diameter: 1100 mm

Narangopal Chowk to Maharagunj SRT
Today: 132 m To Date: 1677 m Total: 1725 m
Pipe Diameter: 500 mm

Machhapokhari By-pass Balaju to Balaju New SRT
Today: 90 m To Date: 630.5 m Total: 785 m
Pipe Diameter: 1000 mm

Kalanki Malakuy Buspark to Khasi Bazar Kalanki
Today: 0 m To Date: 182 m Total: 1325 m
Pipe Diameter: 700 mm

Balkhu Chowk to Ekanta Kuna Ring Road
Today: 0 m To Date: 2100 m Total: 2800 m
Pipe Diameter: 400 mm

Talchhikhel Chowk Ring Road to Khumaltar SRT
Today: 0 m To Date: 1602.78 m Total: 1938 m
Pipe Diameter: 800 mm

Talchhikhel Chowk Ring Road to Tinkune Chowk (Near TIA)
Today: 88 m To Date: 3932.5 m Total: 4170 m
Pipe Diameter: 800 mm

Tinkune Chowk (Near TIA) to Gausala Chowk
Today: 187 m To Date: 3586.5 m Total: 3622 m
Pipe Diameter: 900 mm

Thapathali Chowk to Maitighar
Today: 231 m To Date: 418 m Total: 600 m
Pipe Diameter: 400 mm

Maitighar to Annam Nagar Tank
Today: 0 m To Date: 1006.5 m Total: 1167 m
Pipe Diameter: 400 mm

Minbhawan Chowk to Maitighar Chowk
Today: 125 m To Date: 1527.5 m Total: 1875 m
Pipe Diameter: 500 mm

Minbhawan Chowk to Tinkune Chowk
Today: 401 m To Date: 1101 m Total: 1180 m
Pipe Diameter: 400 mm

Minbhawan Chowk to Minbhawan Tank
Today: 48 m To Date: 220 m Total: 240 m
Pipe Diameter: 400 mm